$796,000 funded in the adopted FY2027 budget. No project-specific public hearing.
18 non-public or invite-only meetings.
What you can do before the award vote →
The City advertised the project for bid on July 31, 2026. A public records request, PRR 26-645, obtained the complete bid package. The request was filed on August 3, 2026. The City produced the package on August 4, 2026, at no charge. The City's plan center sells the same package for $22.00 through QuestCDN. This copy is free.
249 pages. 2.6 MB. Dated July 31, 2026.
Contains the Advertisement for Bids, the Instructions to Bidders, the Bid Proposal Form, and the full technical specifications.
25 sheets. 21.7 MB. Dated July 31, 2026.
Architectural, structural, civil, and site drawings.
Article 5.1.1, "Opening of Bids," covers the August 25 event.
Bids "will be opened publicly and will be read aloud."
Project Manual, Article 5.1.1, Opening of Bids.
Article 5.3, "Acceptance of Bid (Award)," is a separate, later step.
The Owner "intends (but is not bound) to award a Contract to the lowest responsible and responsive Bidder," if the bid "does not exceed the funds available."
Project Manual, Article 5.3, Acceptance of Bid (Award).
The word "council" appears three times in the 249-page manual. All three name a room or a plan center. Award authority comes from City code, not from the manual.
The City opened sealed bids for the project at the public bid opening on August 25, 2026. Three bids came in.
| Bidder | Base bid as read | Notes |
|---|---|---|
| Mangum Construction LLC, Clarkston, Washington | $668,000 | Apparent low bid |
| Leone & Keeble, Inc., Spokane, Washington | $710,500 | - |
| Kenaston Corporation, Lewiston, Idaho | $748,000 | - |
All three base bids are under the City's engineer's estimate of $783,184. Each bid priced three alternates. Alternate amounts will follow the City's official tabulation.
Gropp Heating, Air & Electric (Moscow), founded by the Gropp family and sold to The SEER Group in 2022, is the electrical subcontractor on all three bids. Hilliard's Heating & Plumbing (Pullman, Washington) is the plumbing subcontractor on the Kenaston and Leone & Keeble bids. AA Construction (Moscow) is the plumbing subcontractor on the Mangum bid.
Four documents state four different figures for the same project.
| Figure | Amount | Source |
|---|---|---|
| Original FY2026 appropriation | About $885,000 | FY2026 budget |
| FY2027 budget line | $796,000 | FY2027 budget page 311, adopted August 17, 2026 as Ordinance 2026-05 |
| Engineer's estimate on the advertisement | $783,184 | Advertisement for Bids, July 31, 2026 |
| Cost estimate stated from the dais | $781,000 | City staff stage update, August 3, 2026 Council meeting |
No document explains the difference between the four.
The advertised contract includes a standard non-appropriation clause, so the City could advertise before the August 17 appropriation vote without creating an obligation."This Agreement is contingent upon CITY receiving the necessary funding to cover the obligations of CITY. In the event that such funding is not received or appropriated, then, and in that event, CITY's obligations under this Agreement shall cease and each Party shall be released from further performance under this Agreement without any liability to the other Party."
That is how much the adopted FY2027 budget commits to replace a park stage that volunteers built and maintained for 40 years. The original FY2026 appropriation was $885,000. The money comes from the City's Capital Projects Fund.
That is roughly $31 for every man, woman, and child in Moscow (2020 Census population 25,435).
March 23, 2026 Budget Workshop. City Administrator Bill Belknap presented the FY2027 financial outlook to City Council. He did not mention the stage.
"Before we even look at those, we're 50 to 80,000 in the hole."
On the FY2027 structural deficit before any non-personnel inflation is counted.
"We've had seven positions that we've held vacant since 2023... We won't have funding for bringing those."
Three years of frozen positions. No restoration in sight.
"We're going to have to give up a patrol position in order to retain that."
On losing the forensic detective after Attorney General funding was cut.
"Don't want this to be a downer, but... We have to be really mindful of what our limitations are."
New annual revenue: $315,000-$355,000. Payroll increases alone: ~$408,000. The city is underwater before it pays for anything beyond salaries. The stage draws from the same finite pool.
On March 23, 2026, the City shelved the $26M Downtown Streetscape project. Downtown got $250K for design only. The park stage got $796K for full construction. Here is what the city cannot afford while building a stage:
In Fall 2022, the City conducted a formal scoring process to identify its highest-priority strategic initiatives. The City Administrator told Council the process ensures "our finite resources" are focused on "our most important issues." Thirteen initiatives made the list:
The East City Park Stage is not on this list.
It was never submitted, scored, or ranked through the process the City Administrator described. Yet Council directed the project at the original FY2026 appropriation of about $885,000, and adopted an FY2027 line of $796,000. Both bypassed the prioritization framework the Council had endorsed.
"The stage is old and needs replacing."
It was repaired by volunteers for $818 after the September 2009 fire and is still in use today. The question is whether $796,000 from the Capital Fund is the right approach when D Street repair remains grant-dependent, Downtown stays shelved, and seven staff positions stay frozen.
"The money is already budgeted."
Budgets can be amended, but the FY2027 budget is now adopted (August 17, 5-1). The stage was one line inside a $149.9 million budget. No hearing has ever been held on the project itself. The next public decision on this project is the council's bid-award vote, after bids opened August 25. That vote is the place to raise these concerns.
"This is just political."
The facts on this page name their sources: City records, meeting recordings, news reports, and named accounts. The source documents are linked at the bottom of this page. Read them yourself and draw your own conclusions.
Copy this text and send it, or write your own message.
Attend the next City Council meeting. First and third Mondays, 7:00 PM, moved to Tuesday in holiday weeks, Moscow City Hall (206 E 3rd Street).
Email the Council: council@ci.moscow.id.us
Request the records: Moscow Public Records Request Form
View the source documents: All Records Received (Dropbox)
Share this page.
On June 17, 2024, City Council reached consensus on three commitments before proceeding with the stage project. Here is what the records show happened:
| June 17, 2024 Council Consensus | What the Records Show |
|---|---|
| "More community outreach" | 6 private meetings, 1 comment-card-only open house (14 responses), 3 unadvertised display boards |
| "Community input" | No survey, no formal Q&A, no referendum, no public hearing |
| "Financial comparison of locations" | No alternative site analysis found in any reviewed public record |
From arson fire to construction contract. Each key decision point in the record.
These are the ten organizations invited to participate in stakeholder meetings.
| # | Organization | Representative | Nov 15, 2024 | Jan 23, 2025 |
|---|---|---|---|---|
| 1 | Rendezvous in the Park | Daryle F. | Attended | Attended |
| 2 | Renaissance Fair | LuAnn S. | Attended | Attended |
| 3 | Earth Day | Stevie S-J. | Attended | Did NOT attend |
| 4 | Hemp Fest | Arlene F. | Attended | Attended |
| 5 | Palouse Pride | Kathy S. | Attended | Attended |
| 6 | Moscow Community Band | Albert M. | Did NOT attend | No record |
| 7 | Festival Dance | Rachel W. | Attended | Attended |
| 8 | Latah Recovery Festival | Sam M. | Attended | Did NOT attend |
| 9 | Parks Department | David S. | Attended | Attended |
| 10 | Arts Department | Megan C. | Attended | Attended |
A minimum of 18 non-public or invite-only meetings have been identified in the public record between 2010 and 2026. This list is drawn from council minutes, City records, and direct statements from meeting participants.
| # | Date | Meeting Type | Notes |
|---|---|---|---|
| 1 | Feb 2010 | Invite-only stakeholder | City Parks, City Arts, event reps. No public notice. |
| 2 | Jun 16, 2010 | Internal selection committee | Unnamed committee reviewed RFQ responses. Members not disclosed. |
| 3 | Aug 9, 2010 | Administrative Committee review | Design West contract reviewed before consent agenda placement. |
| 4 | Aug 18, 2010 | Stakeholder Meeting #1 | Invite-only, 12:00-2:00 pm. |
| 5 | Aug 25, 2010 | Stakeholder Meeting #2 | Invite-only, 1:30-3:30 pm. |
| 6 | Sep 7, 2010 | Executive Session | 11:10-11:46 pm, Idaho Code 67-2345(1)(c). Topic not public. |
| 7 | Sep 15, 2010 | Stakeholder Meeting #3 | Invite-only, 12:30-1:30 pm. |
| 8 | 2011 | Grant application approvals | Both grant applications placed on consent agenda. No discussion. |
| 9 | 2012 | Scope reduction decision | Restroom-only direction set. Stage deferred without public hearing. |
| 10 | Nov 5, 2012 | Expedited bid award | Normal committee review bypassed at Council request. |
| 11 | May 6, 2024 | Design West PSA | $18,700 paid. Scope and authorization basis not fully documented in public record. |
| 12 | Nov 14, 2024 | Individual meeting | City staff met individually with Rachel W. (Festival Dance). |
| 13 | Nov 15, 2024 | Stakeholder Meeting | Described by a former Arts Commission member as "private, closed, unpublicized." |
| 14 | Jan 23, 2025 | Stakeholder Meeting | Invite-only. Second formal stakeholder meeting (see attendance table). |
| 15 | Mar 6, 2025 | Open House (restricted format) | Comment cards only, no Q&A. Not a public hearing. 14 responses. |
| 16 | Nov 25, 2025 | Fee proposal meeting | Warnick (Design West) to Riddle (City). Not a public meeting. |
| 17 | Dec 15, 2025 | Council approval (no hearing) | $72,700 contract approved unanimously. No dedicated public comment period. |
| 18 | Mar 25, 2026 | 60% Design Review | Designated "invitation only." General public excluded. |
| Date | Item | Amount | Source |
|---|---|---|---|
| Apr 2010 | Emergency repairs (donated) | $409.16 | Council minutes |
| Apr 2010 | Emergency repairs (City share) | $409.16 | Council minutes |
| 2010 | Insurance proceeds received | $58,000 | Council minutes |
| 2010 | Conceptual design - basic estimate | $495,150 | Design West presentation |
| 2010 | Conceptual design - enhanced estimate | $698,925 | Design West presentation |
| FY2012 | Budget allocation (donations) | $242,000 | FY2012 Budget |
| 2011 | Grant applications (both failed) | Up to $400,000 | Council minutes |
| 2012 | Design West - restroom contract | $17,000 | Council minutes |
| Oct 2012 | Big Sky Development - restroom low bid | $167,000 | Council minutes |
| CIP 2025-2034 | Stage replacement estimate (Project 108-024) | $360,500 | CIP document |
| May 6, 2024 | Design West PSA | $18,700 | City records |
| Dec 15, 2025 | Design West - design through construction | $72,700 | Council vote |
| FY2026 | Stage replacement budget (Capital Fund) | $885,000 | FY2026 Budget |
| FY2026 | 1% Public Art (shared with City Shop) | $150,000 | FY2026 Budget (Art Fund) |
| Mar 2026 | T-Mobile grant application | Up to $50,000 | Grant Review Form |
| FY2027, adopted Aug 17, 2026 | Stage replacement budget (Capital Projects Fund) | $796,000 | FY2027 Budget, Ordinance 2026-05 |
| Aug 2026 | Bid advertisement, engineer's estimate | $783,184 | PRR 26-645, Project Manual, Advertisement for Bids |
| Current | Stage rental fee | $26.75 / shelter | Fee Schedule |
| Design West total paid to date | $91,400 | ($18,700 + $72,700) | |
| Phase | Amount | Percentage |
|---|---|---|
| Schematic / Design Development | $18,175 | 25% |
| Construction Documents | $29,080 | 40% |
| Bidding or Negotiation | $7,270 | 10% |
| Construction Phase | $18,175 | 25% |
| Total | $72,700 | 100% |
| Milestone | Target Date |
|---|---|
| Program verification | January 30, 2026 |
| Design development | February 27, 2026 |
| 60% Construction Documents | March 20, 2026 |
| 90% Construction Documents | April 10, 2026 |
| Final bid documents | May 10, 2026 |
| Construction | September 7, 2026 - March 31, 2027 |
Qualifications-Based Selection (QBS/RFQ). Design West prepared the original 2010 concept plan and the 30% design set, then won the RFQ for the full design-through-construction contract. The contract acknowledges this: "based upon the Concept Plan prepared by CONSULTANT under a prior separate contract." No other firm had the same project history before the RFQ was issued.
The listed hourly rates are "valid through December 2025." Work extends to March 2027.
A former Moscow Arts Commission member submitted a signed letter with 15 co-signers to City Council. Co-signers include: Walter H., Lynn, Logan M., Alan R., Nicole R., Laura P., Ken F., Jo H., Joanne R., Holly M., Kathy D., Fran R., Elizabeth H., Dale G., and Monique L.
Opposition letters were published in the Moscow-Pullman Daily News on:
Council member Bryce Blankenship sent form-letter responses to at least four residents who wrote individually to oppose the project. All four letters were dated December 23, 2025, with nearly identical content across all responses.
Two newly seated council members (Scott Sumner and Sage McCetich) were not receiving emails sent to council@ci.moscow.id.us due to an IT configuration error. At least 9 constituent emails were missed during a critical period of public input.
Mayor Lewis voted against this project, a separate vote from the 3-3 design tie described above. Council members Holmes, Sumner, and McCetich are new. This is their first real budget fight. The question for Moscow: will the new council honor the promises the old council broke?
Attend the next City Council meeting. First and third Mondays, 7:00 PM, moved to Tuesday in holiday weeks, Moscow City Hall (206 E 3rd Street).
Email the Council: council@ci.moscow.id.us
Request the records: Moscow Public Records Request Form
View the source documents: All Records Received (Dropbox)
Share this page.
The facts on this page come from City public records, City meeting recordings, published news reports, and named accounts, each cited to its source. The City records were obtained under the Idaho Public Records Act (Idaho Code 74-102). Source documents are available for public review.